Our intervention
Issues:
- Hot water piping network leaks.
- New use for Mosque, Cabin, Gym and Galley B to meet client needs and rig requirements.
- Deterioration of Change rooms and toilets.
- Bad condition of tile flooring inside cabin’s sanitary unit and PVC flooring damaged inside conf room and mess room.
Jobs carried out:
- Replace complete hot water network main lines using dilatation connection and proper insulation.
- Install CPVC ball valves and access hatches to facilitate maintenance of fresh water piping networks.
- Refurbish entire rooms as toilet and common change room.
- Re design of rooms / areas to adjust to new requirements (keeping some existing equipment while replacing and adjusting new ones).
- Remove existing damaged PVC flooring and lay new heavy duty PVC flooring.
- Inside mess room, replace existing PVC flooring with new heavy duty resin flooring (90m²).
Revamping & upgrading works summary
- Job done during SPS at quay side in Las Palmas with full POB living on board.
- Total workforce: 12 people.
- Complete duration of project: 6 weeks.
- All job carried out with purchased imported IMO- marine classified equipments and materials shipped from Marseille (France) to Las Palmas in three 20feet containers.